🌳 Tog-Wajale Recreational Mini Park
Construction Intelligence Platform V7.0 | Fusion Core

📍 Location: Tog-Wachale City Council
👥 Client: SRS Tog-Wachale City Administration – Job Creation Office
🤝 Implementer: Urban Productive Safety Net Project (UPSNJP)
🏗️ Contractor: Awale GCC
📅 Start: March 25, 2026  |  ⏱️ Duration: 30 Days  |  💰 Total Budget: ETB 6,147,584.48
📁 Project Knowledge Vault — Standardized Naming
Naming Convention: tog-wajale-[category]-[description].html Lowercase • Hyphen-separated • Consistent

📊 Schedule Performance Index

1.00
SPI = EV / PV

💰 Cost Performance Index

1.00
CPI = EV / AC

⏱️ Schedule Status

On Track
vs Target: Apr 23, 2026

⚠️ Active Risks

0
High/Medium priority unresolved

Trend Forecast

--
Linear regression prediction

Smart Recovery

--
Optimised strategies

Scenario Simulator

--
Best / Base / Worst

Live Weather

Loading...
Productivity-adjusted
Resource & Cash Flow

Workforce Demand

S-Curve (PV vs EV)

Cost Analysis (ETB)

🍩 Budget Distribution

📊 Horizontal Bar

📚 Stacked

CPM Schedule & Gantt
Mobilization
Hardscape
Utilities
Softscape
Critical
WBS & EVM Controls
IDTaskDurDepsESEFLSLFFloatCriticalProgressAction
Risk Register
IDRiskCategoryProbImpactScoreMitigationStatus
R01Heavy rain delaysWeather4520Contingency planOpen
R02Cement shortageSupply3412Buffer stockOpen
R03Labor shortageResources3412Backup rosterOpen
R04Equipment breakdownEquipment248Maintenance logOpen
R05Safety non-complianceSafety2510Daily auditsClosed