Tog-Wajale Recreational Mini Park

15-Day Aggressive Recovery Schedule (May 1 – May 16, 2026)

Day Date Main Activities Manpower Key Materials Target Output Status
1-2 May 1 – 2 Main Gate Installation + Final Fence (mesh, barbed wire, backfill) 1 Foreman + 6 Masons + 2 Welders + 8 Laborers Gate hardware, cement, sand, gravel, welding rods Gate 100% + Fence Secured Pending
3-5 May 3 – 5 HCB Curb Stone Installation + Haunching (1,295.6m) 1 Foreman + 10 Masons + 10 Laborers 2,332 pcs HCB blocks, cement, sand 100% Curb Stone Completed Pending
6-7 May 6 – 7 Curb Plastering + Remaining Road Sub-base 1 Foreman + 8 Masons + 6 Laborers Cement, sand, plaster tools Plaster 100% + Sub-base Done Pending
8-11 May 8 – 11 Concrete Tiles Laying (892.80 m² main roads) 1 Foreman + 12 Tile Fixers + 8 Laborers 893 m² Concrete Tiles + Mortar Road Tiles 100% Completed Pending
12-13 May 12 – 13 Crushed Stone Walkways + Curb Painting 1 Foreman + 6 Masons/Painters + 8 Laborers 88 m³ Crushed Stone + Emulsion Paint Walkways & Painting 100% Pending
14 May 14 10m³ Water Tank + Pipes + 10 Solar Lights 1 Foreman + 4 Technicians + 6 Laborers Water Tank, Pipes, Full Solar Set Utilities 100% Pending
15-16 May 15 – 16 Grass (3,036 m²) + Trees (576 pcs) + Final Cleaning & Handover 1 Foreman + 12–15 Landscaping Laborers Grass, Trees, Cleaning materials Practical Completion Pending
Note: This is an aggressive recovery plan. Peak manpower required is 21 workers on Days 3–5 and 8–11. Procure HCB blocks and Concrete tiles immediately.