🌿 Tog-Wajale Recreational Mini Park

15-Day Aggressive Recovery Plan | May 1 – May 16, 2026

Detailed Manpower & Material Requirements | Daily Progress Reporting Format

📋 Daily Manpower & Material Requirements (15 Days)
DayDateMain ActivitiesManpower (Role + Count)Key Materials NeededTarget Output
Peak manpower: 21 workers (Days 3–5 & 8–11) | Total workforce over 15 days: 250+ worker-days.
📝 Daily Progress Report Template (Copy to Word / Excel)

📌 Daily Progress Report – Tog-Wajale Recreational Mini Park

Date: _______________    Day: ________ (e.g., Day 3)
Reported by: _______________    Supervisor: _______________

NoActivity / BOQ ItemPlanned TodayActual Achieved% Complete (Cumulative)Remarks / Issues / PhotosMaterials Used
1Main Gate Installation
2Fence Finalization (mesh, barbed, backfill)
3HCB Curb Stone InstallationHCB pcs: ______
4Curb Plastering (1:3)
5Concrete Tiles Laying (Road)m²: _______
6Crushed Stone Walkwaysm³: _______
7Painting (Curbs & Wall Seat)Paint used:
8Water Tank + Solar Lights
9Grass & Tree PlantingGrass m² / Trees:
10Site Cleaning & Snagging

Overall Project Progress Today: ________ %
Major Issues / Delays:
_________________________________________________
Materials Received Today:
_________________________________________________
Next Day Plan (Key Activities):
_________________________________________________

Signatures: Contractor: _______________   Site Engineer: _______________   Supervisor: _______________

📦 Material Procurement Summary (15 Days)
🏗️ Critical Materials (Immediate)
  • HCB blocks: 2,332 pcs
  • Concrete tiles: 892.80 m² + binding
  • Crushed stone: 87.95 m³
  • Plastic emulsion paint: 13 cartons
💧 MEP & Finishing
  • Elevated water tank 10m³
  • Pipes & fittings (irrigation)
  • Solar lighting kit (10 poles + lamps)
  • Welding rods & anchor bars
🌱 Landscaping
  • Grass (3,036 m²)
  • Flowering trees (576 pcs)
  • Cement, sand, gravel (ongoing)
📆 Plain-Text Daily Reporting Table (Copy directly to Excel)
Date	Day	Activity	Planned	Actual	%Complete	Materials Used	Remarks
____	Day 1	Gate foundation	100%	___	___	Cement/sand/rebar	___
____	Day 2	Gate installation	100%	___	___	Hardware/welding rods	___
____	Day 3	Curb stone start	400m	___	___	800 HCB blocks	___
____	Day 4	Curb + haunching	400m	___	___	800 HCB + concrete	___
____	Day 5	Curb completion	Remaining	___	___	~700 HCB	___
____	Day 6	Plastering start	50%	___	___	Mortar	___
____	Day 7	Plaster complete	100%	___	___	Cement/Sand	___
____	Day 8	Tiles laying	250 m²	___	___	250 m² tiles	___
____	Day 9	Tiles laying	250 m²	___	___	250 m² tiles	___
____	Day 10	Tiles laying	200 m²	___	___	200 m² tiles	___
____	Day 11	Tiles complete	893 m² total	___	___	remaining tiles	___
____	Day 12	Walkways + painting start	60%	___	___	Crushed stone 88m³	___
____	Day 13	Painting complete	100%	___	___	Emulsion paint	___
____	Day 14	Water tank + solar	100%	___	___	Tank + solar set	___
____	Day 15	Grass & trees (70%)	---	___	___	Grass m² / trees	___
____	Day 16	Handover & completion	100%	___	___	Final cleaning	___
        

✅ Copy the above tab-separated block and paste into Excel → columns will auto-arrange.

✍️ Quick Fill Daily Log (Field Use)