15-Day Aggressive Recovery Plan | May 1 – May 16, 2026
Detailed Manpower & Material Requirements | Daily Progress Reporting Format
| Day | Date | Main Activities | Manpower (Role + Count) | Key Materials Needed | Target Output |
|---|
Date: _______________ Day: ________ (e.g., Day 3)
Reported by: _______________ Supervisor: _______________
| No | Activity / BOQ Item | Planned Today | Actual Achieved | % Complete (Cumulative) | Remarks / Issues / Photos | Materials Used |
|---|---|---|---|---|---|---|
| 1 | Main Gate Installation | |||||
| 2 | Fence Finalization (mesh, barbed, backfill) | |||||
| 3 | HCB Curb Stone Installation | HCB pcs: ______ | ||||
| 4 | Curb Plastering (1:3) | |||||
| 5 | Concrete Tiles Laying (Road) | m²: _______ | ||||
| 6 | Crushed Stone Walkways | m³: _______ | ||||
| 7 | Painting (Curbs & Wall Seat) | Paint used: | ||||
| 8 | Water Tank + Solar Lights | |||||
| 9 | Grass & Tree Planting | Grass m² / Trees: | ||||
| 10 | Site Cleaning & Snagging |
Overall Project Progress Today: ________ %
Major Issues / Delays:
_________________________________________________
Materials Received Today:
_________________________________________________
Next Day Plan (Key Activities):
_________________________________________________
Signatures: Contractor: _______________ Site Engineer: _______________ Supervisor: _______________
Date Day Activity Planned Actual %Complete Materials Used Remarks
____ Day 1 Gate foundation 100% ___ ___ Cement/sand/rebar ___
____ Day 2 Gate installation 100% ___ ___ Hardware/welding rods ___
____ Day 3 Curb stone start 400m ___ ___ 800 HCB blocks ___
____ Day 4 Curb + haunching 400m ___ ___ 800 HCB + concrete ___
____ Day 5 Curb completion Remaining ___ ___ ~700 HCB ___
____ Day 6 Plastering start 50% ___ ___ Mortar ___
____ Day 7 Plaster complete 100% ___ ___ Cement/Sand ___
____ Day 8 Tiles laying 250 m² ___ ___ 250 m² tiles ___
____ Day 9 Tiles laying 250 m² ___ ___ 250 m² tiles ___
____ Day 10 Tiles laying 200 m² ___ ___ 200 m² tiles ___
____ Day 11 Tiles complete 893 m² total ___ ___ remaining tiles ___
____ Day 12 Walkways + painting start 60% ___ ___ Crushed stone 88m³ ___
____ Day 13 Painting complete 100% ___ ___ Emulsion paint ___
____ Day 14 Water tank + solar 100% ___ ___ Tank + solar set ___
____ Day 15 Grass & trees (70%) --- ___ ___ Grass m² / trees ___
____ Day 16 Handover & completion 100% ___ ___ Final cleaning ___
✅ Copy the above tab-separated block and paste into Excel → columns will auto-arrange.