🌳 Tog-Wajale Recreational Mini Park
Construction Intelligence Platform V6.0

📍 Location: Tog-Wachale City Council
👥 Client: SRS Tog-Wachale City Administration – Job Creation Office
🤝 Implementer: Urban Productive Safety Net Project (UPSNJP)
🏗️ Contractor: Awale GCC
📅 Start: March 25, 2026  |  ⏱️ Duration: 30 Days  |  💰 Total Budget: ETB 6,147,584.48

📊 Schedule Performance Index

1.00
SPI = EV / PV

💰 Cost Performance Index

1.00
CPI = EV / AC

⏱️ Schedule Status

On Track
vs Target: Apr 23, 2026

⚠️ Active Risks

0
High/Medium priority unresolved

Trend Forecast

--
Linear regression prediction

Smart Recovery

--
Optimised strategies

Scenario Simulator

--
Best / Base / Worst

Live Weather Intelligence

Loading...
Productivity‑adjusted schedule
Resource & Cash Flow Analytics

Daily Workforce Demand

Cash Flow S-Curve (PV vs EV)

Cumulative planned vs earned value – donor reporting ready
Cost Analysis (ETB)

🍩 Budget Distribution

📊 Horizontal Bar

📚 Stacked Sub-components

CPM Schedule & Gantt
Mobilization/Earthworks
Hardscape
Utilities
Softscape
Critical Path

Hover for details. Red bars = Critical Path. Progress sliders update EVM & AI forecasts.

Work Breakdown Structure & EVM Controls
IDTask NameDuration (d)DependenciesESEFLSLFFloatCriticalProgress %Action

Adjust progress sliders → EVM & AI forecasts update instantly. Duration edits require "Recalculate".

Project Risk Register
IDRisk DescriptionCategoryProbabilityImpactScoreMitigationStatus
R01Heavy rain delays earthworks & plantingWeather4520Weather contingency planOpen
R02Cement/diesel shortageSupply Chain3412Buffer stock + alternative suppliersOpen
R03Labor shortage / skilled workersResources3412Backup roster, cross-trainingOpen
R04Equipment breakdown (Dozer/Loader)Equipment248Daily maintenance logOpen
R05Safety non-complianceSafety2510Daily audits & PPEClosed

Active Risks = Open entries with Score ≥ 6. Status dropdown updates count automatically.

Critical Material Procurement
MaterialQuantityLead TimeMust Be On‑Site By
OPC Cement504 Quintals3 DaysDay 4 (28 Mar)
HCB Blocks2,332 Pcs5 DaysDay 4 (28 Mar)
RHS Steel Posts189 Pcs7 DaysDay 6 (30 Mar)
Concrete Tiles892.80 m²10 DaysDay 10 (3 Apr)
Tree Saplings576 Pcs2 DaysDay 21 (14 Apr)
Labor Resource Plan
Crew TypePersonnelPeak PeriodPrimary Output
Earthwork & Logistics14Days 1-1060 m³ cart‑away/day
Masonry & Concrete13Days 5-22100 m² tiling/day
Greenery & Irrigation24Days 20-3075 trees planted/day

PRACTICAL COMPLETION CERTIFICATE (DRAFT)

Awale General Construction Company has substantially completed the Tog-Wajale Recreational Mini Park in accordance with UPSNJP standards. Total Value: ETB 6,147,584.48.

___________________
Awale GCC
___________________
Client Representative