🏗️ Tog-Wajale Recreational Mini Park

15-Day Aggressive Recovery Plan | May 1 – May 16, 2026
Prepared by: Shemshedin H | SOMA Consult Platform
21
Peak Daily Manpower
1,296m
Curb Stone Total
893m²
Concrete Tiles
3,036m²
Grass Area
260
Total Man-days
📅 PHASE 1: GATE & FENCE (Days 1-2)
DayDateActivityForemanMasonsWeldersLaborersTotalMaterialsTarget
1May 1Gate foundations + erection162817Cement, rebar, gateGate 60%
2May 2Complete gate + hardware151613Hinges, lock, rodsGate 100%
📅 PHASE 2: CURB STONE & PLASTER (Days 3-7)
DayDateActivityForemanMasonsLaborersTotalMaterialsTarget
3May 3HCB Curb start (400m)1101021800 HCB blocks400m
4May 4Curb + haunching1101021800 HCB blocks800m
5May 5Complete curb19919700 HCB blocks100%
6May 6Plaster start1861530 bags cement50%
7May 7Complete plaster1861530 bags cement100%
📅 PHASE 3: CONCRETE TILES (Days 8-11)
DayDateActivityForemanTile FixersLaborersTotalMaterialsTarget
8May 8Tiles start112821250 m² tiles250m²
9May 9Tiles continue112821250 m² tiles500m²
10May 10Tiles continue112821200 m² tiles700m²
11May 11Complete tiles110617193 m² tiles893m²
📅 PHASE 4: FINISHING & HANDOVER (Days 12-16)
DayDateActivityForemanMasons/PaintersTechsLaborersTotalMaterialsTarget
12May 12Walkways + paint start16081588 m³ stone, paint60%
13May 13Complete painting16061313 cartons paint100%
14May 14Water tank + solar104611Tank, pipes, solar set100%
15May 15Grass + trees10015163036m² grass, 400 trees70%
16May 16Snagging + handover1001011Remaining plantsHandover