May 1 – May 16, 2026 | Duration: 15 Days
| Day | Date | Main Activities | Manpower Requirement | Key Materials Required | Target Output |
|---|---|---|---|---|---|
| 1-2 | May 1 – 2 | Main Gate Installation (4m×3m) + Final Fence works (mesh tensioning, barbed wire, backfill) | 1 Foreman + 6 Masons + 2 Welders + 8 Laborers | Gate hardware, cement, sand, gravel, welding rods | Gate 100% + Perimeter Secured |
| 3-5 | May 3 – 5 | 20cm HCB Curb Stone Installation + Concrete Haunching (1,295.6m total) | 1 Foreman + 10 Masons + 10 Laborers | 2,332 pcs HCB blocks, cement, sand | 100% Curb Stone Completed |
| 6-7 | May 6 – 7 | Curb Plastering (1:3) + Remaining Road Sub-base | 1 Foreman + 8 Masons + 6 Laborers | Cement, sand, plastering tools | Plaster 100% + Sub-base finished |
| 8-11 | May 8 – 11 | Concrete Tiles Laying (15cm × 30cm) on Main Internal Roads (892.80 m²) | 1 Foreman + 12 Tile Fixers + 8 Laborers | 893 m² Concrete Tiles + 1:3 Mortar | Road Tiles 100% Completed |
| 12-13 | May 12 – 13 | Crushed Stone Aggregate for Walkways + Three-coat Painting on Curbs | 1 Foreman + 6 Masons/Painters + 8 Laborers | 88 m³ Crushed Stone + Plastic Emulsion Paint | Walkways & Painting 100% |
| 14 | May 14 | Elevated 10m³ Water Tank + Pipes + 10 Solar Light Poles Installation | 1 Foreman + 4 Technicians + 6 Laborers | Water Tank, Pipes & Fittings, Complete Solar System | All Utilities Completed |
| 15-16 | May 15 – 16 | Grass Laying (3,036 m²) + Tree Planting (576 pcs) + Final Cleaning & Handover | 1 Foreman + 12–15 Landscaping Laborers | Grass, Trees, Cleaning materials | Practical Completion & Handover |