🏛️ Tog-Wajaale Meeting Hall | Green Construction Intelligence (BOQ 2026)

📍 Location: Tog-Wajaale City, Kebele 07 (Next to Al-Braka)
👥 Client: SRS Tog-Wajaale City Administration
🏗️ Contractor: AWALE GCC
📅 Start: March 15, 2026  |  ⏱️ Updated Duration: 150 Days  |  💰 Total Budget (BOQ): ETB 31,781,903

📊 Schedule Performance Index

0.68
SPI = EV / PV

💰 Cost Performance Index

0.96
CPI = EV / AC

⏱️ Schedule Status

Delayed
Target: Aug 12, 2026

⚠️ Active Risks

4
High/Medium priority unresolved

Trend Forecast

12 Aug 2026
Most Likely Completion

Smart Recovery

🚧 Expedite steel crew + night shifts
Mitigation active

Live Weather

Loading...
Tog-Wajaale

Revised EVM Summary (as of 15 May 2026)

Earned Value (EV): ETB 4,894,470  |  Actual Cost (AC): ETB 5,100,000  |  Planned Value (PV): ETB 7,200,000
SPI: 0.68 → Behind schedule  |  CPI: 0.96 → Minor cost pressure
Forecast EAC (Pessimistic): ETB 34.2M  |  Steel structural delay is critical driver.

Cost Breakdown (ETB) – Updated BOQ March 2026

🍩 Budget Distribution

📊 Material vs Labor

📈 Horizontal Bar

Resource Loading by Crew Type (Peak Headcount)
Critical Path Schedule – Realistic Durations (150d)
Substructure
Steel Structure
Roof/Aluminium
MEP
Finishes
Critical Path
Work Breakdown Structure & EVM Controls (Updated Tasks)
IDTask NameDuration (d)DependenciesESEFLSLFFloatCriticalProgress %
Project Risk Register (Steel Delivery Priority)
IDRisk DescriptionProbabilityImpactScoreStatus
R01Steel delivery delay (H/I beams from Addis)4520Open
R02Crane unavailability for steel erection3412Open
R03Anchor bolt misalignment / QA failure2510Closed
R04Skilled labour shortage (steel erectors)4416Open
R05Heavy rain during concrete curing339Open