Period: May 1 – May 16, 2026 | Total Duration: 15 Days
| Day | Date | Main Activities | Manpower Requirement | Key Materials Required | Target Output |
|---|---|---|---|---|---|
| 1-2 | May 1 – 2 | Main Entrance Gate Installation (4m×3m) + Final Fence Works (mesh, barbed wire, backfill & anchorage) | 1 Foreman + 6 Masons + 2 Welders + 8 Laborers | Gate hardware, cement, sand, gravel, welding rods | Gate 100% + Full Perimeter Secured |
| 3-5 | May 3 – 5 | 20cm thick HCB Curb Stone Installation + Concrete Haunching (1,295.6m) | 1 Foreman + 10 Masons + 10 Laborers | 2,332 pcs HCB Blocks, Cement, Sand | 100% Curb Stone Completed |
| 6-7 | May 6 – 7 | Two Coats Curb Plastering (1:3) + Remaining Road Sub-base | 1 Foreman + 8 Masons + 6 Laborers | Cement, Sand, Plastering Tools | Plaster 100% + Sub-base Finished |
| 8-11 | May 8 – 11 | Concrete Tiles Laying (15cm × 30cm) on Main Internal Roads (892.80 m²) | 1 Foreman + 12 Tile Fixers + 8 Laborers | 893 m² Concrete Tiles + 1:3 Mortar + Binding Material | Road Tiles 100% Completed |
| 12-13 | May 12 – 13 | Crushed Stone for Walkways (87.95 m³) + Three Coats Emulsion Paint on Curbs | 1 Foreman + 6 Masons/Painters + 8 Laborers | 88 m³ Crushed Stone + Plastic Emulsion Paint (13-15 Karton) | Walkways & Painting 100% |
| 14 | May 14 | Installation of 10m³ Elevated Water Tank + Pipes + 10 Solar Lights | 1 Foreman + 4 Technicians + 6 Laborers | 10m³ Water Tank, Pipes & Fittings, Complete Solar Lighting System | All Utilities 100% |
| 15-16 | May 15 – 16 | Grass Laying (3,036.10 m²) + Tree Planting (576 pcs) + Final Site Cleaning & Handover Preparation | 1 Foreman + 12–15 Landscaping Laborers | Grass, 576 Trees, Cleaning Materials | Practical Completion & Handover |