May 1 – May 16, 2026 | Total Duration: 15 Days
| Day | Date | Main Activities | Target Output |
|---|---|---|---|
| 1-2 | May 1 – 2 | Main Entrance Gate Installation + Final Fence Works (mesh, barbed wire, backfill, anchorage) | Gate 100% + Perimeter Secured |
| 3-5 | May 3 – 5 | 20cm HCB Curb Stone Installation + Concrete Haunching (1,295.6m) | 100% Curb Stone Completed |
| 6-7 | May 6 – 7 | Curb Plastering (1:3) + Remaining Road Sub-base | Plaster 100% + Sub-base Finished |
| 8-11 | May 8 – 11 | Concrete Tiles Laying (15cm × 30cm) on Main Roads (892.80 m²) | Road Tiles 100% Completed |
| 12-13 | May 12 – 13 | Crushed Stone for Walkways + Three Coats Painting on Curbs | Walkways & Painting 100% |
| 14 | May 14 | 10m³ Water Tank + Pipes + 10 Solar Lights Installation | Utilities 100% |
| 15-16 | May 15 – 16 | Grass Laying (3,036 m²) + Tree Planting (576 pcs) + Final Cleaning & Handover | Practical Completion |
| Day | Date | Main Activity | Manpower Requirement | Total Workers |
|---|---|---|---|---|
| 1-2 | May 1–2 | Gate + Final Fence | 1 Foreman + 6 Masons + 2 Welders + 8 Laborers | 17 |
| 3-5 | May 3–5 | Curb Stone Installation | 1 Foreman + 10 Masons + 10 Laborers | 21 |
| 6-7 | May 6–7 | Curb Plastering + Sub-base | 1 Foreman + 8 Masons + 6 Laborers | 15 |
| 8-11 | May 8–11 | Concrete Tiles Laying | 1 Foreman + 12 Tile Fixers + 8 Laborers | 21 |
| 12-13 | May 12–13 | Walkways + Painting | 1 Foreman + 6 Masons/Painters + 8 Laborers | 15 |
| 14 | May 14 | Water Tank + Solar Lights | 1 Foreman + 4 Technicians + 6 Laborers | 11 |
| 15-16 | May 15–16 | Grass & Trees + Cleaning | 1 Foreman + 12–15 Laborers | 13–16 |
| No | Material Description | Unit | Quantity | Priority | Recommended Delivery |
|---|---|---|---|---|---|
| 1 | 20cm thick HCB Blocks | Pcs | 2,332 | URGENT | By May 2 |
| 2 | Concrete Tiles (15cm × 30cm) | m² | 893 | URGENT | By May 3 |
| 3 | Crushed Stone Aggregate (01) | m³ | 88 | High | By May 10 |
| 4 | Plastic Emulsion Paint | Karton | 13 – 15 | High | By May 10 |
| 5 | Cement (50kg) | Bags | 150 – 200 | Medium | As needed |
| 6 | 10m³ Elevated Roto Water Tank | No | 1 | Medium | By May 12 |
| 7 | Pipes & Fittings | Lot | 1 | Medium | By May 12 |
| 8 | Solar Lighting System | Set | 10 | Medium | By May 12 |
| 9 | Grass | m² | 3,036 | Low | By May 14 |
| 10 | Trees (Different types) | Pcs | 576 | Low | By May 14 |