Tog-Wajale Recreational Mini Park / Landscape

15-DAY AGGRESSIVE RECOVERY PLAN

May 1 – May 16, 2026 | Total Duration: 15 Days

1. DAILY WORK PLAN

Day Date Main Activities Target Output
1-2May 1 – 2Main Entrance Gate Installation + Final Fence Works (mesh, barbed wire, backfill, anchorage)Gate 100% + Perimeter Secured
3-5May 3 – 520cm HCB Curb Stone Installation + Concrete Haunching (1,295.6m)100% Curb Stone Completed
6-7May 6 – 7Curb Plastering (1:3) + Remaining Road Sub-basePlaster 100% + Sub-base Finished
8-11May 8 – 11Concrete Tiles Laying (15cm × 30cm) on Main Roads (892.80 m²)Road Tiles 100% Completed
12-13May 12 – 13Crushed Stone for Walkways + Three Coats Painting on CurbsWalkways & Painting 100%
14May 1410m³ Water Tank + Pipes + 10 Solar Lights InstallationUtilities 100%
15-16May 15 – 16Grass Laying (3,036 m²) + Tree Planting (576 pcs) + Final Cleaning & HandoverPractical Completion

2. LABOR / MANPOWER REQUIREMENTS

Day Date Main Activity Manpower Requirement Total Workers
1-2May 1–2Gate + Final Fence1 Foreman + 6 Masons + 2 Welders + 8 Laborers17
3-5May 3–5Curb Stone Installation1 Foreman + 10 Masons + 10 Laborers21
6-7May 6–7Curb Plastering + Sub-base1 Foreman + 8 Masons + 6 Laborers15
8-11May 8–11Concrete Tiles Laying1 Foreman + 12 Tile Fixers + 8 Laborers21
12-13May 12–13Walkways + Painting1 Foreman + 6 Masons/Painters + 8 Laborers15
14May 14Water Tank + Solar Lights1 Foreman + 4 Technicians + 6 Laborers11
15-16May 15–16Grass & Trees + Cleaning1 Foreman + 12–15 Laborers13–16

3. MATERIAL REQUIREMENTS

No Material Description Unit Quantity Priority Recommended Delivery
120cm thick HCB BlocksPcs2,332URGENTBy May 2
2Concrete Tiles (15cm × 30cm)893URGENTBy May 3
3Crushed Stone Aggregate (01)88HighBy May 10
4Plastic Emulsion PaintKarton13 – 15HighBy May 10
5Cement (50kg)Bags150 – 200MediumAs needed
610m³ Elevated Roto Water TankNo1MediumBy May 12
7Pipes & FittingsLot1MediumBy May 12
8Solar Lighting SystemSet10MediumBy May 12
9Grass3,036LowBy May 14
10Trees (Different types)Pcs576LowBy May 14
Important Notes:
• Peak manpower required is 21 workers on Days 3–5 and 8–11.
• HCB Blocks and Concrete Tiles are critical and must be on site by May 2–3.
• Daily progress must be updated on SOMA Consult with supporting photos.
Prepared by:

________________________
Site Engineer
Reviewed by:

________________________
Project Manager
Approved by:

________________________
Client / Supervisor