Contract No: TWCA OFED/CHB/007/2025 | Awale GCC
PRESENTED BY
City Municipality Engineer
10 June 2026 β’ Report No.003
Tog-Wajaale Β· Construction Progress
Physical Progress
58.9%
Baseline Plan
72%
13.1% behind schedule | Critical path at risk
Financial Status
Variation pending: ETB 9.38M (excl. VAT) | Outstanding executed ~10.87M incl VAT
Steel Structure
35% complete vs 70% plan β’ Rate escalation +174%
| Section | Weight | Progress | Status |
|---|---|---|---|
| Sub-structure | 22% | 100% | β Complete |
| Steel Structure / Roofing | 46% | 35% | π΄ CRITICAL |
| Block Works | 4.5% | 55% | β οΈ Serious |
| Finishing / Aluminium / MEP | 21% | 0% | βΈ Not started |
π° Outstanding for Executed Work
~10.87M ETB
(incl. VAT) β’ Urgent payment required
Paid: 6.08M excl VAT | Executed: 15.54M excl VAT
Underestimated Quantities
4,850,000 ETB
Rate Escalation (Steel +174%)
3,450,000 ETB
Missed Items
1,082,346 ETB
Submission
10 June 2026
Joint Measurement
By 20 June
Engineer Valuation
Certification
PMC Approval
Target 20 June
Milestone Delays
50 days EOT
Gross delay 82 days β’ Net claimable 50 days
Steel rates +174%
56-day delay, procurement stopped β awaiting variation approval
Block work quantity underestimated (+84%)
31-day delay, additional materials ordered
Cash flow gap ~10.87M ETB unpaid executed work
Material orders delayed β urgent payment required to avoid stoppage
10 May
17 May
24 May
7 June
10 June
β οΈ Progress rate dropped to +0.9% last week β decision needed urgently
Project Management Committee Resolution
β Approve Variation Order: ETB 9,382,346 (excl. VAT)
β Grant EOT of 50 days β New completion 1 September 2026
β Authorize interim payment of ETB 5M (excl. VAT)
Chairperson, PMC β Tog-Wajaale
Excavation complete
Steel truss 35%
Staircase 60% (missed item)
Raked floor executed
Engineer available for detailed clarification on variation, rates, and EOT.
SRS Tog-Wajaale City Administration β Engineering Dept
Awale GCC | Next update: 30 June 2026