City Meeting Hall – Tog-Wajaale

Contract No: TWCA OFED/CHB/007/2025 | Awale GCC

PRESENTED BY

City Municipality Engineer

10 June 2026 β€’ Report No.003

01 / 17
PROJECT STATUS & VARIATION CLAIM

City Meeting Hall

Tog-Wajaale Β· Construction Progress

June 2026 Monthly Report #003

πŸ“Š Overall Project Status

Physical Progress

58.9%

Baseline Plan

72%

13.1% behind schedule | Critical path at risk

🟑

Financial Status

Variation pending: ETB 9.38M (excl. VAT) | Outstanding executed ~10.87M incl VAT

πŸ”΄

Steel Structure

35% complete vs 70% plan β€’ Rate escalation +174%

πŸ“ˆ Physical Progress by Work Section

SectionWeightProgressStatus
Sub-structure22%
100%
βœ… Complete
Steel Structure / Roofing46%
35%
πŸ”΄ CRITICAL
Block Works4.5%
55%
⚠️ Serious
Finishing / Aluminium / MEP21%
0%
⏸ Not started
βœ… Sub-structure complete. Steel truss erection at 35% due to variation & market spike. Missed items (raked floor, staircase) already executed.

πŸ’° Financial Summary (ETB)

Original Contract (excl. VAT)16,993,391
Variation Claimed+9,382,346
Revised Total26,375,738

πŸ’° Outstanding for Executed Work

~10.87M ETB

(incl. VAT) β€’ Urgent payment required

Paid: 6.08M excl VAT | Executed: 15.54M excl VAT

πŸ“‹ Variation Breakdown (ETB 9,382,346)

52%

Underestimated Quantities

4,850,000 ETB

37%

Rate Escalation (Steel +174%)

3,450,000 ETB

11%

Missed Items

1,082,346 ETB

Engineer note: Steel market I-Beam 200x100: 95 β†’ 260 ETB/kg (+174%). Verified by supplier quotations (attached).

πŸ”„ Variation Approval Roadmap

Submission

10 June 2026

Joint Measurement

By 20 June

Engineer Valuation

Certification

PMC Approval

Target 20 June

πŸ“‘ Variation Claim – Full Documentation

  • Revised BoQ (March 2026)
  • Variation calculation sheets
  • Joint site measurement records
  • Market price quotations (steel +174%)
  • Photographic evidence (raked floor, staircase)

Supporting Evidence

8 site photos Steel quotes As-built
All appendices in Monthly Report #003

πŸ“… Schedule & Extension of Time

Milestone Delays

Steel structure+56 days
Block works+31 days
Practical Completion13 Jul β†’ 1 Sep 2026

50 days EOT

Gross delay 82 days β€’ Net claimable 50 days

Engineer recommendation: Approve EOT due to variation impact on critical path.

⚠️ Critical Issues & Risks

πŸ”΄

Steel rates +174%

56-day delay, procurement stopped – awaiting variation approval

🟑

Block work quantity underestimated (+84%)

31-day delay, additional materials ordered

πŸ’°

Cash flow gap ~10.87M ETB unpaid executed work

Material orders delayed – urgent payment required to avoid stoppage

πŸ“‰ Progress Trend (Last 30 Days)

45%

10 May

50%

17 May

54%

24 May

58%

7 June

58.9%

10 June

⚠️ Progress rate dropped to +0.9% last week – decision needed urgently

βœ… Urgent Requests to PMC

πŸ”΄ URGENT (by 15-20 June)
  • Interim EOT (30-45 days) to protect programme
  • Payment for executed work (~10.87M ETB incl. VAT)
πŸ”΅ HIGH (by 20 June)
  • Variation Order Approval (9,382,346 ETB excl. VAT)
  • Full EOT (50 days β†’ 1 September 2026)

πŸ—οΈ Engineer’s Recommendation

  • Approve Variation Order – ETB 9,382,346 (excl. VAT) fully substantiated
  • Grant EOT of 50 days β†’ completion 1 September 2026
  • Authorize interim payment of ETB 5,000,000 (excl. VAT) to unlock steel
  • Direct joint site measurement within 14 days

πŸ“œ Draft Resolution

Project Management Committee Resolution

βœ… Approve Variation Order: ETB 9,382,346 (excl. VAT)

βœ… Grant EOT of 50 days – New completion 1 September 2026

βœ… Authorize interim payment of ETB 5M (excl. VAT)

Chairperson, PMC – Tog-Wajaale

πŸ“Œ One-Glance Summary

Overall % Complete58.9%
Total Contract (incl VAT)30.33M ETB
Outstanding Executed10.87M ETB
Steel rate increase+174%
EOT requested50 days
New completion1 Sep 2026

πŸ“Έ Site Evidence – Engineer Verified

Excavation complete

Steel truss 35%

Staircase 60% (missed item)

Raked floor executed

Questions & Discussion

Engineer available for detailed clarification on variation, rates, and EOT.

Decision Required: Approve Variation & EOT

Thank You

SRS Tog-Wajaale City Administration – Engineering Dept

Awale GCC | Next update: 30 June 2026