City Meeting Hall

Tog-Wajaale ยท G+0

Monthly Progress Report No.03April 2026

Client: Tog Wajaale City Administration | Contractor: Awale GCC

Presented by SOMA Consult ยท Green CPM Intelligence

Handover Target: 13 July 2026

๐ŸŽค Speaker noteFull presentation of April 2026 progress. We are ahead of schedule but face critical administrative bottlenecks.

๐Ÿ“ˆ Execution Status

As of April 30, 2026

Time Performance

Time Elapsed: 38.33% (46 days)

Physical Progress

Executed: 40.92% +2.59% Variance

The project is currently ahead of schedule. However, pending steel approvals (45 days overdue) and delayed payments put this lead at immediate risk for May.

Substructure complete. Steel materials on site. Ready to accelerate.

Forecast Risk: Without steel approval and IPC certification within 10 days, roof erection activities will directly impact the July 13 completion target.
๐ŸŽค Speaker noteWe have a positive variance, but the buffer will vanish if approvals don't come within the next 10 days.

๐Ÿ“„ Contract Data

ItemDetails
Original contract amount (incl. VAT)ETB 19,542,399.84
Variation claim submittedETB 12,239,503.41
Total claimed amountETB 31,781,903.25
Revised completion13 July 2026
Time elapsed46 days (38.33%)
๐ŸŽค Speaker noteVariation claim submitted 08 May 2026 due to quantity underestimation and steel price escalation.

๐Ÿ—๏ธ Current Stages (ETB)

DescriptionPlannedExecutedStatus
Substructure total3,669,0585,786,248Complete (+57.7%)
Superstructure total1,133,1432,894,217In Progress
Block Works396,847599,35651% ahead
Roofing & Steel736,2962,294,860Materials Delivered
๐ŸŽค Speaker noteSubstructure overruns of +57.7% validate the variation claim. Steel materials are on site awaiting erection approval.

Materials on Site

Total value: ETB 6,911,973.80

H-Beam 200ร—100: 84m โ€“ ETB 2,003,484
I-Beam 200ร—100: 140m โ€“ ETB 3,339,140
Purlins RHS: 2,147kg โ€“ ETB 1,111,466
Plates & J-Bolts: ETB 458,884
HCB blocks: 60% delivered
Recommendation: Certify these materials for IPC No.03 to release cash flow and enable steel erection.
๐ŸŽค Speaker noteAll major steel sections are stored safely. Immediate certification unlocks acceleration.

๐Ÿ’ฐ Variation Claim Breakdown

Total: ETB 12,239,503.41

  • ๐Ÿ“ฆ Quantity underestimation: 44.5% (ETB 5.45M)
  • ๐Ÿ“ˆ Steel price escalation: 32.5% (ETB 3.98M)
  • ๐Ÿ› ๏ธ Additional works (VO-001): 12.0% (ETB 1.47M)
  • ๐Ÿ“Œ Missed items: 10.0% (ETB 1.22M)
  • โœ–๏ธ Arithmetical error: 1.0% (ETB 0.12M)
Substructure overrun of +57.7% fully supports this claim. Awaiting employer approval.
๐ŸŽค Speaker noteThe variation is well justified by actual site overruns and market escalation. Approval aligns the contract with real costs.

โš ๏ธ Critical Blockers

  • Material shortage: No
  • Cash shortage: Yes (delayed IPC payments)
  • Steel approval: 45 DAYS OVERDUE
  • Variation claim: Awaiting approval
Remarks:
- Cash flow constrained by delayed IPC No.01/02.
- Alternative steel sections pending since 27 March 2026.
- Variation claim of ETB 12.24M awaiting employer decision.
๐ŸŽค Speaker noteThree major blockers: cash flow, steel approval, and variation claim. These are the only things holding back rapid progress.

๐Ÿ’ต Payment Status

Work executed + materials on site: ETB 6,953,391
Payment certified (excl. VAT): ETB 4,658,531
Amount paid: ETB 3,475,130
Outstanding certified: ETB 1,183,401
Delayed payments constrain site operations. Urgent processing of IPC No.02 and materials certification required.
๐ŸŽค Speaker noteCash flow is the biggest operational constraint. Timely payment will restore procurement and labour productivity.

โญ Quality & Performance

Quality of works: GOOD
Quality of materials: GOOD
Overall performance: FAIR (due to external delays)
Manpower: Skilled & unskilled available.
Equipment: Fully functional on site.
Contractor delivered substructure overruns (+57.7%), block works ahead (+51%), and steel materials delivered. Performance rated FAIR only because of administrative bottlenecks.
๐ŸŽค Speaker noteQuality is excellent. The contractor is ready to accelerate โ€“ only approvals are lacking.

๐Ÿ“ Urgent Measures Required

Physical progress stands at 40.92% against time elapsed of 38.33%, resulting in a positive variance of +2.59%. However, without immediate administrative action, this lead may be lost during May.

Four critical actions requested:
  1. Approve alternative steel section (pending since 27 March)
  2. Certify & pay IPC No.02 outstanding balance
  3. Certify materials on site for IPC No.03 (ETB 6.91M)
  4. Approve Variation Claim (ETB 12.24M)
๐ŸŽค Speaker noteThese four actions are critical to maintain momentum and hit the July completion.

โœ… Critical Client Action Summary

Urgent decisions required to protect the July 13 Handover

Administrative Bottlenecks (Impact: High Risk of Delay)
  1. Steel Approval: Approve alternative sections (H/I 200x). 45 DAYS OVERDUE
  2. Cash Flow: Certify materials on site (ETB 6.91M) for IPC No.03. CRITICAL FOR LABOUR
  3. Contract Alignment: Finalize Variation Claim (ETB 12.24M) to reflect actual site quantities.

โœ“ Contractor Awale GCC is fully mobilized. Immediate approval allows 24/7 acceleration.

Continued delay in approvals may result in reduced labour productivity, slower steel erection, and potential extension-of-time implications.

๐ŸŽค Speaker noteEvery day the steel approval sits idle is a day we lose on the roof erection. We need these three green lights today.

๐ŸŒ Site Conditions

Rainfall: Bimodal (Mar-May).
Temperature: 35-40ยฐC in April.
Soil: Red earth, ideal for construction.
Terrain: Flat, no topographical hurdles.
Weather during April: occasional rain and high temperatures โ€“ moderate challenges but no stoppages. Contractor has maintained progress.
๐ŸŽค Speaker noteDespite hot and rainy conditions, the contractor has maintained progress. No weather-related delays.

๐Ÿ“Œ Signatories & Approval

Engineer Representative
____________________
Date: ___________
Project Engineer
____________________
Date: 08 May 2026
Prepared by: Awale GCC โ€“ Project Management Team
Project Manager Signature: ____________________
Date: 08 May 2026
For Employer's Use Only: Received by: ____________________ | Date: ___________ | Remarks: ___________
๐ŸŽค Speaker noteAll signatures and dates as per original report. The employer's section remains for your use.

Thank You

SOMA Consult ยท Green CPM Intelligence

Data based on Monthly Progress Report No.03 (April 2026) and site updates as of 30 April 2026.

We look forward to your prompt approval to deliver the City Meeting Hall on 13 July 2026.

๐ŸŽค Speaker noteThank you for your attention. We are confident in the project's success with your support.