Client: Tog Wajaale City Administration | Contractor: Awale GCC
Presented by SOMA Consult ยท Green CPM Intelligence
Handover Target: 13 July 2026
As of April 30, 2026
Time Elapsed: 38.33% (46 days)
Executed: 40.92% +2.59% Variance
The project is currently ahead of schedule. However, pending steel approvals (45 days overdue) and delayed payments put this lead at immediate risk for May.
Substructure complete. Steel materials on site. Ready to accelerate.
| Item | Details |
|---|---|
| Original contract amount (incl. VAT) | ETB 19,542,399.84 |
| Variation claim submitted | ETB 12,239,503.41 |
| Total claimed amount | ETB 31,781,903.25 |
| Revised completion | 13 July 2026 |
| Time elapsed | 46 days (38.33%) |
| Description | Planned | Executed | Status |
|---|---|---|---|
| Substructure total | 3,669,058 | 5,786,248 | Complete (+57.7%) |
| Superstructure total | 1,133,143 | 2,894,217 | In Progress |
| Block Works | 396,847 | 599,356 | 51% ahead |
| Roofing & Steel | 736,296 | 2,294,860 | Materials Delivered |
Total value: ETB 6,911,973.80
Total: ETB 12,239,503.41
Physical progress stands at 40.92% against time elapsed of 38.33%, resulting in a positive variance of +2.59%. However, without immediate administrative action, this lead may be lost during May.
Urgent decisions required to protect the July 13 Handover
โ Contractor Awale GCC is fully mobilized. Immediate approval allows 24/7 acceleration.
Continued delay in approvals may result in reduced labour productivity, slower steel erection, and potential extension-of-time implications.
SOMA Consult ยท Green CPM Intelligence
Data based on Monthly Progress Report No.03 (April 2026) and site updates as of 30 April 2026.
We look forward to your prompt approval to deliver the City Meeting Hall on 13 July 2026.