πŸ—οΈ TOG‑WAJAALE MEETING HALL – REALISTIC DYNAMIC DASHBOARD

πŸ“… Start: 16 March 2026 | 🏁 Handover: 10 July 2026 | πŸ’° Budget: 25,731,513 Birr
βœ… Initial state: 23 working days elapsed β†’ 30% overall progress (steel materials on site) | Use β—€/β–Ά to simulate future/past

πŸ“‹ Project Snapshot

πŸ“† Calendar days120
πŸ› οΈ Working days (Mon–Sat)0
🎯 Overall progress (cost‑based)0%
βš™οΈ Current phaseβ€”
πŸ“… Simulated working day0 / 0
⏳ COUNTDOWN TO HANDOVER β€”
*Progress = Earned Value (cost weighted) | Moves tasks, Gantt, budget dynamically | Countdown reflects simulated calendar days left until handover (10 July 2026)

πŸ’° Financial (BOQ split)

πŸ“Œ Total budget25,731,513 Birr
πŸ’Έ Earned value (spent)0 Birr
πŸ“‰ Remaining budget0 Birr
⚑ Pie = original BOQ categories | Earned value updates with each day

⚠️ Critical Actions & Logistics

β–ͺ️ Steel materials (I/H beams, plates, bolts) fully on site (cost captured)
β–ͺ️ Erection crew mobilization follows schedule from day 28
β–ͺ️ Substructure advanced ~80% at day 23
β–ͺ️ Use navigation to see cost & task evolution

πŸ“… Construction Gantt β€” bar fill = % of task completed

πŸ“‹ Task Breakdown & Dynamic Progress

TaskPhaseStart dateDuration (days)Progress
🧱 Steel materials task represents procurement & site storage (cost ~4.5M). Erection task starts at day 28. Overall progress = weighted sum of task completions.

🏁 Key Milestones

πŸ“¦ Steel material arrivalβœ… Completed day 6
πŸ—οΈ Erection startπŸ”œ Not yet
🧱 Substructure concrete🟒 progress varies