Critical delay risk: Approval for alternative steel sections (H & I Beams 200×100×10mm) has been pending for 42 days since Letter Ref SRS/AGCC/WH-MH/2026/007 dated 27 March 2026. Materials are on site but steel erection cannot proceed without sign-off from the Employer/Engineer.
Physical progress
40.92%
Target: 41.00%  Slightly ahead
Time elapsed
38.33%
46 of 120 calendar days
Original contract value
ETB 19.5M
ETB 19,542,399.84 incl. 15% VAT
Total claimed (incl. VO)
ETB 31.8M
Variation claim: ETB 12,239,503.41
Work executed + materials
ETB 6.95M
IPC certified: ETB 4,658,531 (excl. VAT)
Amount paid to date
ETB 3.48M
23.84% of original contract
Construction progress
Current stages of construction
A. Sub-structure (overall) +57.7% Substantially complete
Sub-item Planned (ETB) Executed (ETB) Status
Excavation & earthwork 1,434,931 2,456,879 Done
Concrete work (C-5, C-25) 1,759,272 2,299,720 Done
Masonry foundation 474,855 1,029,649 Done
B. Super-structure In progress
Sub-item Planned (ETB) Executed (ETB) Status
Block works (HCB walls) 396,847 599,356 51% ahead
Roofing & steel structure 736,296 2,294,860 Mtls delivered
Variation claim — ETB 12,239,503
Qty underestimation 45.2% Steel escalation 32.5% Add'l works 13.1% Missed items 12.1% Arith. error 1.1%
Quantity underestimation 45.2%, steel price escalation 32.5%, additional works 13.1%, missed items 12.1%, arithmetical error 1.1%.
Original contract ETB 19,542,399.84
Variation claim submitted + ETB 12,239,503.41
Total claimed ETB 31,781,903.25
Monthly progress — planned vs executed
Planned % Executed %
Previous months: 26.73% planned and executed. April 2026: 14.27% planned, 12.42% executed. Cumulative: 41.00% planned, 40.92% executed.
Materials on site (delivered end of April 2026)
Steel sections & fasteners delivered — total on-site value: ETB 6,911,974
H-Beam (Universal Column)
200×100×10mm
84 ml · ETB 23,851/ml
ETB 2,003,484
I-Beam (Universal Beam)
200×100×10mm
140 ml · ETB 23,851/ml
ETB 3,339,140
Purlins RHS
80×40×3mm
2,147.76 kg · ETB 517.50/kg
ETB 1,111,466
Base Plates A
140×150×6mm
28 pcs · ETB 1,725/pc
ETB 48,300
Base Plates B
300×300×10mm
28 pcs · ETB 6,520.50/pc
ETB 182,574
J-Bolts
84 pcs
ETB 1,725/pc
ETB 144,900
Crank Bolts ∅8
84 pcs
ETB 977.50/pc
ETB 82,110
HCB (Hollow Concrete Blocks)
60% delivered
Value TBC
Partial delivery

All steel materials stored on site. Awaiting Employer verification and certification for IPC No. 03. Steel erection on hold pending 42-day-overdue approval.

Issues & urgent actions required
Pending approvals & actions
Alternative steel section approval
Ref: SRS/AGCC/WH-MH/2026/007 · Submitted 27 March 2026
42 days overdue
IPC No. 02 — certification & payment
Cash flow constraints affecting contractor operations
Outstanding
Materials on site verification for IPC No. 03
ETB 6.9M in steel materials unverified on site
Pending
Variation claim ETB 12,239,503.41
Submitted 08 May 2026 — supported by sub-structure overruns
Awaiting approval
Evaluations
Quality of works
Good
Quality of materials
Good
Contractor performance
Fair
Manpower availability
Good
Equipment on site
Good
Cash flow status
Constrained
Contract timeline
Key dates
15 March 2026
Revised commencement date
27 March 2026
Alternative steel section approval requested (still pending)
30 April 2026
End of reporting period — 40.92% progress achieved
08 May 2026
Variation claim ETB 12,239,503.41 submitted; Report No. 03 issued
15 June 2026
Original completion date
13 July 2026
Revised completion date
Contract data
EmployerSRS Tog-Wajaale City Admin. Municipality Bureau
ContractorAwale GCC
Contract typeUnit Price
Duration120 calendar days (4 months)
Defect liability365 calendar days
Retention5% of IPC
CurrencyEthiopian Birr (ETB)
Source of fundsSRS Tog-Wajaale City Administration
Coordinates313,518.462 E · 1,061,821.662 N
Site progress photographs — April 2026
Figure 1 — Overall site view
Overall site view showing erected red steel columns and beams with partial HCB walls, April 2026
Figure 1: Overall site view showing erected red steel columns and beams with partial HCB walls (April 2026)

The photograph shows the current construction state: red-painted steel H and I columns erected at perimeter grid positions, with horizontal beams partially connected. HCB (hollow concrete block) perimeter walls are progressing along the foundation.

Certification & signatures
Engineer's Representative
Date: _______________
Project Engineer
Date: 08 May 2026
Awale General Construction Co.
Project Manager · Prepared by
Date: 08 May 2026