📅 Tog-Wajale Recreational Mini Park – 15-Day Aggressive Recovery Schedule
Period: May 1 – May 16, 2026 | Total Duration: 15 Days | Target: Practical Completion
DayDateMain ActivitiesManpower RequirementKey Materials RequiredTarget Output
1-2May 1–2Main Entrance Gate Installation (4m×3m) + Final Fence Works (mesh, barbed wire, backfill, anchorage)1 Foreman + 6 Masons + 2 Welders + 8 Laborers (17 total)Gate hardware, cement, sand, gravel, welding rodsGate 100% + Full Perimeter Secured
3-5May 3–520cm thick HCB Curb Stone Installation + Concrete Haunching (1,295.6m)1 Foreman + 10 Masons + 10 Laborers (21 total)2,332 pcs HCB Blocks, Cement, Sand100% Curb Stone Completed
6-7May 6–7Two Coats Curb Plastering (1:3) + Remaining Road Sub-base1 Foreman + 8 Masons + 6 Laborers (15 total)Cement, Sand, Plastering ToolsPlaster 100% + Sub-base Finished
8-11May 8–11Concrete Tiles Laying (15cm × 30cm) on Main Internal Roads (892.80 m²)1 Foreman + 12 Tile Fixers + 8 Laborers (21 total)893 m² Concrete Tiles + 1:3 Mortar + Binding MaterialRoad Tiles 100% Completed
12-13May 12–13Crushed Stone for Walkways (87.95 m³) + Three Coats Emulsion Paint on Curbs1 Foreman + 6 Masons/Painters + 8 Laborers (15 total)88 m³ Crushed Stone + Plastic Emulsion Paint (13-15 Karton)Walkways & Painting 100%
14May 14Installation of 10m³ Elevated Water Tank + Pipes + 10 Solar Lights1 Foreman + 4 Technicians + 6 Laborers (11 total)10m³ Water Tank, Pipes & Fittings, Complete Solar Lighting SystemAll Utilities 100%
15-16May 15–16Grass Laying (3,036 m²) + Tree Planting (576 pcs) + Final Site Cleaning & Handover1 Foreman + 12–15 Landscaping LaborersGrass, 576 Trees, Cleaning MaterialsPractical Completion & Handover
📌 Key Notes: Peak manpower 21 workers (Days 3–5 & 8–11). HCB Blocks & Concrete Tiles must be on site by May 2. Daily photos required.
Prepared by:
Site Engineer
Reviewed by:
Project Manager
Approved by:
Client Representative
📊 Overall Project Progress (Weighted)
0%
🔨 Activity Progress (Update completed qty)
📸 New Daily Log
📋 Daily Log History
💰 Total Cost: 0 ETB
📋 Daily Progress Report Template (Copy to Word/Excel)

📌 Daily Progress Report – Tog-Wajale Recreational Mini Park

Date: _______________    Day: ________
Reported by: _______________    Supervisor: _______________

NoActivity / BOQ ItemPlanned TodayActual Achieved% Complete (Cumulative)Remarks / IssuesMaterials Used
1Main Gate Installation
2Fence Finalization
3HCB Curb Stone InstallationHCB pcs: ___
4Curb Plastering
5Concrete Tiles Layingm²: ___
6Crushed Stone Walkwaysm³: ___
7Painting (Curbs & Wall Seat)
8Water Tank + Solar Lights
9Grass & Tree PlantingGrass m² / Trees
10Site Cleaning & Snagging

Overall Progress Today: ________ %
Major Issues / Delays:
_________________________________________
Materials Received Today:
_________________________________________
Next Day Plan:
_________________________________________

Signatures: Contractor: _________   Site Engineer: _________   Supervisor: _________