🏗️ Tog-Wajale Recreational Mini Park

Digital Daily Progress Report • 15-Day Recovery Plan

📊 Weighted Daily Progress
Activity Weight Today (%) Contribution
Gate & Fence8%%0.0%
HCB Curb Stone + Haunching20%%0.0%
Curb Plastering10%%0.0%
Concrete Tiles Laying25%%0.0%
Walkways + Painting12%%0.0%
Water Tank + Solar Lights10%%0.0%
Grass + Trees15%%0.0%
Today's Weighted Progress: 0.0%
Previous Cumulative: 0.0%
Progress Gained Today: 0.0%

Cumulative Project Progress: %
👷 Manpower Today
📦 Materials Status
⚠️ Issues / Delays / Comments
📸 Site Photos Today (Max 6)

Reported by: Shemshedin H.
Site Engineer | SOMA Consult

Printed on: