| 1-2 |
May 1 – 2 |
Main Entrance Gate Installation (4m×3m) + Final Fence Works (mesh, barbed wire, backfill & anchorage) |
1 Foreman + 6 Masons + 2 Welders + 8 Laborers |
Gate hardware, cement, sand, gravel, welding rods |
Gate 100% + Full Perimeter Secured |
| 3-5 |
May 3 – 5 |
20cm thick HCB Curb Stone Installation + Concrete Haunching (1,295.6m) |
1 Foreman + 10 Masons + 10 Laborers |
2,332 pcs HCB Blocks, Cement, Sand |
100% Curb Stone Completed |
| 6-7 |
May 6 – 7 |
Two Coats Curb Plastering (1:3) + Remaining Road Sub-base |
1 Foreman + 8 Masons + 6 Laborers |
Cement, Sand, Plastering Tools |
Plaster 100% + Sub-base Finished |
| 8-11 |
May 8 – 11 |
Concrete Tiles Laying (15cm × 30cm) on Main Internal Roads (892.80 m²) |
1 Foreman + 12 Tile Fixers + 8 Laborers |
893 m² Concrete Tiles + 1:3 Mortar + Binding Material |
Road Tiles 100% Completed |
| 12-13 |
May 12 – 13 |
Crushed Stone for Walkways (87.95 m³) + Three Coats Emulsion Paint on Curbs |
1 Foreman + 6 Masons/Painters + 8 Laborers |
88 m³ Crushed Stone + Plastic Emulsion Paint (13-15 Karton) |
Walkways & Painting 100% |
| 14 |
May 14 |
Installation of 10m³ Elevated Water Tank + Pipes + 10 Solar Lights |
1 Foreman + 4 Technicians + 6 Laborers |
10m³ Water Tank, Pipes & Fittings, Complete Solar Lighting System |
All Utilities 100% |
| 15-16 |
May 15 – 16 |
Grass Laying (3,036.10 m²) + Tree Planting (576 pcs) + Final Site Cleaning & Handover Preparation |
1 Foreman + 12–15 Landscaping Laborers |
Grass, 576 Trees, Cleaning Materials |
Practical Completion & Handover