15-Day Aggressive Recovery Schedule (May 1 – May 16, 2026)
| Day | Date | Main Activities | Manpower | Key Materials | Target Output | Status |
|---|---|---|---|---|---|---|
| 1-2 | May 1 – 2 | Main Gate Installation + Final Fence (mesh, barbed wire, backfill) | 1 Foreman + 6 Masons + 2 Welders + 8 Laborers | Gate hardware, cement, sand, gravel, welding rods | Gate 100% + Fence Secured | Pending |
| 3-5 | May 3 – 5 | HCB Curb Stone Installation + Haunching (1,295.6m) | 1 Foreman + 10 Masons + 10 Laborers | 2,332 pcs HCB blocks, cement, sand | 100% Curb Stone Completed | Pending |
| 6-7 | May 6 – 7 | Curb Plastering + Remaining Road Sub-base | 1 Foreman + 8 Masons + 6 Laborers | Cement, sand, plaster tools | Plaster 100% + Sub-base Done | Pending |
| 8-11 | May 8 – 11 | Concrete Tiles Laying (892.80 m² main roads) | 1 Foreman + 12 Tile Fixers + 8 Laborers | 893 m² Concrete Tiles + Mortar | Road Tiles 100% Completed | Pending |
| 12-13 | May 12 – 13 | Crushed Stone Walkways + Curb Painting | 1 Foreman + 6 Masons/Painters + 8 Laborers | 88 m³ Crushed Stone + Emulsion Paint | Walkways & Painting 100% | Pending |
| 14 | May 14 | 10m³ Water Tank + Pipes + 10 Solar Lights | 1 Foreman + 4 Technicians + 6 Laborers | Water Tank, Pipes, Full Solar Set | Utilities 100% | Pending |
| 15-16 | May 15 – 16 | Grass (3,036 m²) + Trees (576 pcs) + Final Cleaning & Handover | 1 Foreman + 12–15 Landscaping Laborers | Grass, Trees, Cleaning materials | Practical Completion | Pending |