๐Ÿ—๏ธ MASTER CONSTRUCTION SCHEDULE 2026

100 Calendar Days โ€ข BOQ-integrated โ€ข Critical Path Framework (Mar 16 โ€“ Jun 22)
๐Ÿ“… Total Duration: 99 working days / 100 contract days
โšก Critical Path: Steel delivery โ†’ Frame โ†’ Roof โ†’ Finishes โ†’ MEP
๐Ÿ† Milestones: Substructure Complete (Apr 21) | Weather-Tight (May 16) | Handover (Jun 22)
โ–ˆโ–ˆโ–ˆโ–ˆ Active Work
โ•โ•โ•โ• Critical Path
โ˜ Holiday / Non-working
โ—† Milestone
๐Ÿ“† Weekly Gantt Chart (Phase & Activity)
W1 (Mar 16-21)
โ–ˆโ–ˆโ–ˆโ–ˆ Mobilization & Site Setup
โ˜ Mar 20-21: Eid Holiday
W2 (Mar 23-28)
โ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆ Excavation & Earthworks (A.1)
W3 (Mar 30-Apr 4)
โ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆ Excavation Continuation (A.1)
W4 (Apr 6-11)
โ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆ Foundation Concrete (A.2) โ˜ Good Friday Apr 10
W5 (Apr 13-18)
โ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆโ–ˆ Masonry + Ground Slab (A.3) โ—† Steel Delivery (Apr 18) โ•โ•โ•โ•
W6 (Apr 20-25)
โ•โ•โ•โ• Anchor Bolts (84 pcs) โ•โ•โ•โ• Steel Erection Begins (Apr 22) โ—† โ–ˆโ–ˆโ–ˆโ–ˆ Block work start
W7 (Apr 27-May 2)
โ•โ•โ•โ• Steel Frame Complete (Apr 28) โ—† โ–ˆโ–ˆโ–ˆโ–ˆ HCB Block Work (446 mยฒ)
W8 (May 4-9)
โ–ˆโ–ˆโ–ˆโ–ˆ Block Work + Steel Purlins + Trusses
W9 (May 11-16)
โ–ˆโ–ˆโ–ˆโ–ˆ Roof Structure + Covering (396 mยฒ) โ—† Weather-Tight (May 16)
W10 (May 18-23)
โ–ˆโ–ˆโ–ˆโ–ˆ Plastering (B.5 - 892 mยฒ interior/external)
W11 (May 25-30)
โ–ˆโ–ˆโ–ˆโ–ˆ Gypsum Ceiling (400 mยฒ) + Floor Tiling begins (367 mยฒ) โ—† Peak Workforce (47)
W12 (Jun 1-6)
โ–ˆโ–ˆโ–ˆโ–ˆ Tiling Complete + Painting (B.6) + MEP Rough-In โ—† Finishes Complete (Jun 4)
W13 (Jun 8-13)
โ–ˆโ–ˆโ–ˆโ–ˆ Electrical Installation (B.7) + Drainage Channel (80 ml)
W14 (Jun 15-20)
โ–ˆโ–ˆโ–ˆโ–ˆ Testing & Commissioning + Final Cleaning
W15 (Jun 22)
โ—† PROJECT HANDOVER (Jun 22) โ—†
๐Ÿ“Š Daily Resolution Gantt โ€“ BOQ Linked Activities
* Weeks from Mar 16 to Jun 22 (15 weeks). Critical path in RED, holidays in YELLOW, milestones as PURPLE โ—†

๐Ÿ”ฅ CRITICAL PATH ANALYSIS (Zero Float)

๐Ÿ“Œ Apr 18-20: Steel delivery (B.3)
๐Ÿ“Œ Apr 20-21: Anchor bolts (84 J + crank bolts)
๐Ÿ“Œ Apr 22-28: Steel erection (frame completion)
๐Ÿ“Œ Apr 29-May 16: Roof structure + covering (396 mยฒ)
๐Ÿ“Œ May 17-Jun 4: Finishes (plaster, tile, paint)
๐Ÿ“Œ Jun 5-15: MEP rough-in & electrical (B.7)
๐ŸŽฏ Jun 22: Final Handover milestone
โœ… BOQ References: A.1 (Earthworks) | A.2 (Concrete) | A.3 (Masonry) | B.2 (Blockwork 446mยฒ) | B.3 (Steel+roof) | B.4 (Joinery) | B.5 (Plaster/Tiling) | B.6 (Painting) | B.7 (Electrical)