Total Duration: 99 working days / 100 contract days
โก Critical Path: Steel delivery โ Frame โ Roof โ Finishes โ MEP
๐ Milestones: Substructure Complete (Apr 21) | Weather-Tight (May 16) | Handover (Jun 22)
W1 (Mar 16-21)
โโโโ Mobilization & Site Setup
โ Mar 20-21: Eid Holiday
W2 (Mar 23-28)
โโโโโโโโโโโโโโโโโโโโโโโโ Excavation & Earthworks (A.1)
W3 (Mar 30-Apr 4)
โโโโโโโโโโโโโโโโโโโโโโโโ Excavation Continuation (A.1)
W4 (Apr 6-11)
โโโโโโโโโโโโโโโโโโโโโโโโ Foundation Concrete (A.2) โ Good Friday Apr 10
W5 (Apr 13-18)
โโโโโโโโโโโโโโโโโโโโโโโโ Masonry + Ground Slab (A.3) โ Steel Delivery (Apr 18) โโโโ
W6 (Apr 20-25)
โโโโ Anchor Bolts (84 pcs) โโโโ Steel Erection Begins (Apr 22) โ โโโโ Block work start
W7 (Apr 27-May 2)
โโโโ Steel Frame Complete (Apr 28) โ โโโโ HCB Block Work (446 mยฒ)
W8 (May 4-9)
โโโโ Block Work + Steel Purlins + Trusses
W9 (May 11-16)
โโโโ Roof Structure + Covering (396 mยฒ) โ Weather-Tight (May 16)
W10 (May 18-23)
โโโโ Plastering (B.5 - 892 mยฒ interior/external)
W11 (May 25-30)
โโโโ Gypsum Ceiling (400 mยฒ) + Floor Tiling begins (367 mยฒ) โ Peak Workforce (47)
W12 (Jun 1-6)
โโโโ Tiling Complete + Painting (B.6) + MEP Rough-In โ Finishes Complete (Jun 4)
W13 (Jun 8-13)
โโโโ Electrical Installation (B.7) + Drainage Channel (80 ml)
W14 (Jun 15-20)
โโโโ Testing & Commissioning + Final Cleaning
W15 (Jun 22)
โ PROJECT HANDOVER (Jun 22) โ
* Weeks from Mar 16 to Jun 22 (15 weeks). Critical path in RED, holidays in YELLOW, milestones as PURPLE โ
๐ฅ CRITICAL PATH ANALYSIS (Zero Float)
๐ Apr 18-20: Steel delivery (B.3)
๐ Apr 20-21: Anchor bolts (84 J + crank bolts)
๐ Apr 22-28: Steel erection (frame completion)
๐ Apr 29-May 16: Roof structure + covering (396 mยฒ)
๐ May 17-Jun 4: Finishes (plaster, tile, paint)
๐ Jun 5-15: MEP rough-in & electrical (B.7)
๐ฏ Jun 22: Final Handover milestone
โ
BOQ References: A.1 (Earthworks) | A.2 (Concrete) | A.3 (Masonry) | B.2 (Blockwork 446mยฒ) | B.3 (Steel+roof) | B.4 (Joinery) | B.5 (Plaster/Tiling) | B.6 (Painting) | B.7 (Electrical)