Not Available Materials (Urgent Procurement)
| No | Description | Unit | Qty | Status |
|---|---|---|---|---|
| 1 | HCB Block 200×200×400mm | m² | 446.36 | Not Available |
| 2 | PVC Downpipe Ø110mm | ml | 96.00 | Not Available |
| 3 | Imported Gypsum Board Ceiling | m² | 400.00 | Not Available |
| 4 | EGA Roofing Sheet 0.4mm | m² | 396.33 | Not Available |
| 5 | WPC Interior Panels | m² | 21.84 | Not Available |
| 6 | RHS 80×80×3 mm | Kg | 1,262.53 | Not Available |
| 7 | RHS 60×60×3 mm | Kg | 638.96 | Not Available |
| 8 | Purlins RHS 80×40×3 mm | Kg | 1,953.38 | Not Available |
Partially Available Materials (Balance Required)
| No | Description | Total Qty | Available | Status |
|---|---|---|---|---|
| 1 | I-Beam 200×100×10mm | 30 ml | 715,530 ETB | Partial |
| 2 | ∅8 Crank Bolts | 84 pcs | 41,055 ETB | Partial |
| 3 | Purlins RHS 80×40×3 mm | 2,147.76 Kg | 194,372 ETB | Partial |
Available Materials
- Universal Column (H-Beam 200×100×10mm)
- Steel Plates (140×150×6 mm)
- Steel Plates (300×300×10 mm)
- J-Bolts
Justification
These materials are critical for structural, roofing, and finishing works. Any delay will impact construction progress, roofing completion, and interior works schedule. Immediate procurement is required.